| These tents are where our crew lived while they are working on this project |
| Work was already started on the pool |
| beginning of a set of stairs |
| All of this steel had to be cut, welded and painted then installed |
| removal of the original steel beams |
| Dirt had to be added and compacted -all by hand |
| Painting booth was built with bamboo mats as a roof |
| After concrete is added this became our prep area for pouring the benches |
| we dug a small pool for curing the benches after they were poured |
![]() |
| Soaking the benches in water slowed down the drying process makes for a harder concrete |
| Progress on baptismal pool |
| Lots of dirt was added |
| The first few weeks of our project we had to precut, clean and paint the steel before our welding brother arrived. |
| Our welding brother Jeremiah and wife Holly finally arrived about the end of June.There are a total of 16 large beams 35 ft each that were bolted together at the peak. |
| Special scaffolding had to be built and moved to place each beam on the columns. It took about 15 brothers to carry the beams by hand up the scaffolding into place. SAFETY FIRST even in Africa. |
![]() |
| An exciting day! This is the first of 8 beams |
![]()
| ||
![]() |
| Making good progress things are starting to take shape. |






No comments:
Post a Comment